Submarine telecom and power cables are engineered for different duties. The vessels, handling systems and commercial models are also different. Yet when a cable passes over the stern and enters the water, both sectors face the same fundamental problem: the most important part of the installation is taking place out of sight.
The touchdown point is where the suspended cable first meets the seabed. Its position is affected by vessel movement, payout, tension, water depth, current, cable properties and seabed topography. A lay that looks correct from the bridge can differ from what is happening below. If that difference is discovered late, the consequences may include an out-of-corridor cable, unplanned contact with an asset or obstruction, cable free-spans, compromised bend radii, additional survey work and, in the worst case, recovery or repair.
Power cable projects, particularly offshore wind and interconnector installations, have had strong reasons to improve visibility at touchdown. They frequently operate in shallow, tidal and congested waters, close to existing infrastructure and within tightly defined corridors. The cable is a high-value asset, while vessel and specialist spread costs make delays expensive.
North Sea Systems developed CableFish in response to those conditions. Their smallest system is suitable for cable diameters from 20 – 100mm. The cable-mounted system has not yet been deployed on a live telecom cable contract, although trials and engineering studies have considered comparable and lighter cable configurations. Its experience should therefore be treated as a relevant case study rather than proof of telecom suitability. The useful question is which lessons have already been demonstrated in offshore energy, which could transfer to telecom and what would need to be qualified in a live project.
The touchdown point is an information problem
Cable lay teams already work with a substantial flow of information, including vessel position, cable payout, tension, speed, seabed depth and contours (bathymetry), route engineering and a modelled catenary. Remotely operated vehicles, vessel-mounted sonar and acoustic positioning may add further observations. These inputs do not always provide a continuous, independently verifiable answer to a simple question: where is the cable touching down now?
A calculated position is useful, but its accuracy depends on the model and the quality of its inputs. A camera can be decisive in good visibility but ineffective in turbid water. An ROV can inspect the touchdown point, although it may have to choose between looking back at the cable and looking ahead along the route. Its workability can also be restricted by current, water depth, tether management or maintenance. Acoustic positioning can be difficult in shallow water or challenging acoustic environments.
The first transferable lesson from power cable installation is that no single sensor should carry the whole burden of assurance. A stronger approach combines a cable-specific calculation with direct observation and checks the two continuously.
CableFish is one example of that approach. It travels loosely around the cable and operates a few meters above the seabed. A profiling sonar observes the catenary and touchdown area, while a forward-looking multibeam sonar scans the route ahead for obstacles, trench alignment and other hazards. Its navigation package contributes position, orientation (including roll, pitch and heading), altitude and depth. Together, those inputs support a real-time calculation of touchdown position that can be compared with the sonar observation. The system generates a real-time animation of the cable from the surface to the seabed with key installation parameters, such as layback and corridor width limits, overlaid.
North Sea Systems reports calculated touchdown accuracy of plus or minus 0.5 meters when the system is configured for the cable and lay conditions. The more important point is the relationship between calculation and observation. If they diverge, the installation team can investigate while the cable is still being laid rather than discovering the discrepancy during a post-lay survey.
Continuous monitoring supports earlier decisions
Traditional monitoring can produce valuable snapshots: an ROV observation at one stage of the lay, a survey line afterward or a comparison between planned and as-laid positions. These remain important, but a post-lay answer cannot prevent an installation anomaly.
Continuous monitoring changes the timing of the decision. A system can feed touchdown coordinates, layback, water depth, monitoring-head depth and altitude, and cable angle into the vessel’s survey environment. The project team can compare the touchdown point with route and installation limits and use warnings to identify a developing deviation before it becomes an alarm or an out-of-tolerance event.
This does not automate responsibility away from the offshore construction manager, cable lay engineer or vessel team. It gives them a common operating picture. Instead of reconciling several indirect indicators, the relevant personnel can see the same touchdown behaviour and respond earlier. That is particularly useful during route corrections, approaches, crossings and trench entry, where a small positional error can quickly consume the available tolerance.
For a telecom project, the potential benefit is not simply greater positional precision. It is a shorter chain between detecting a developing problem and acting on it.

Dedicated monitoring can reduce critical path dependencies
A second lesson from offshore energy concerns the allocation of specialist assets. An ROV is highly capable and remains essential for intervention, inspection and cable-end tasks. However, using a general-purpose vehicle as the only means of observing touchdown can make the installation dependent on its availability, maintenance schedule and operating envelope.
A dedicated monitoring tool cannot replace the full range of work performed by an ROV. Its narrower purpose can nevertheless be useful. It may allow touchdown monitoring to continue while the ROV is prepared for another task, maintained or deployed elsewhere in the operation.
On a European offshore wind campaign involving 27 inter-array cables, CableFish and an ROV were used in parallel. The ROV performed work at turbine foundations and cable ends, while the cable-mounted system monitored touchdown during the lay. North Sea Systems reports that 10 cables were installed during spring-tide conditions in which ROV workability would have been severely restricted. The company attributed five days of avoided tidal waiting, two days of avoided ROV maintenance downtime and a further weather-related saving to the arrangement, calculating a net project saving of approximately £1.7 million.
That figure is specific to one project and should not be transferred directly to a telecom business case. However, it is the broader operational lesson which is more useful. Project planners should identify where a multipurpose asset has become a critical path dependency and assess whether dedicated monitoring could provide continuity or redundancy.
The financial exposure is not limited to the daily vessel rate. Losing several hours can impact dependent operations or can push an operation into adverse current or weather, turning a short interruption into several days of delay. The value of an additional monitoring method may therefore lie as much in protecting the installation window as in replacing another asset.
Better records support lifecycle management
Real-time data is primarily used to manage the live operation, but its value does not end when the cable reaches the seabed. A modern touchdown-monitoring system can record time-synchronized sensor data, sonar, video, calculations, cable animation and alarms. The project team can then replay events and compare the sources that informed a decision.
For a telecom owner, that can provide a more complete installation record. It may help demonstrate compliance with the installation plan, explain a route deviation, investigate a suspected anomaly and establish a stronger baseline for future inspection or repair. It can also improve lessons learned. Rather than relying only on shift reports and recollection, engineering teams can return to the operational evidence.
The quality and traceability of as-laid information matter throughout the life of a subsea system. Better evidence cannot prevent every future fault, but it can support route assurance, handover and later integrity decisions. Owners considering new monitoring methods should therefore examine the format, ownership, retention and accessibility of the data, not only the live display available during installation.
Telecom applications need cable specific qualification
The telecom sector is right to question any technology that comes into contact with its cable. A lighter fiber-optic cable will respond differently from an armoured power cable. Relevant issues include local contact pressure, abrasion, minimum bend radius, tensile behaviour, hydrodynamic drag and the effect of additional subsea mass on the catenary.
In the case of CableFish, the survey head does not clamp onto the cable. It sits loosely around it, with nylon guards and rollers at the contact points, and has an approximate submerged weight of 80 kilograms. North Sea Systems uses OrcaFlex analysis to examine the interaction of its system with different products. Modelling for a lighter cable indicates that the additional mass may bring touchdown closer to the vessel and reduce lateral movement in current. That behaviour could improve controllability in some configurations, but it must be demonstrated for the actual cable, route and installation spread.
A credible telecom qualification program should include cable-specific static and dynamic analysis, review by the cable manufacturer and installer, confirmation of contact materials and allowable loads, and testing against bend, strain and attenuation limits. The parties should also agree the operating envelope, data interface, positioning method, treatment of sensor dropouts, and normal and emergency recovery procedures before mobilisation.
An initial live deployment could run the cable-mounted system alongside established monitoring arrangements. This would allow the owner and installer to compare calculated and observed touchdown positions without immediately making the new method the sole source of assurance. The resulting evidence would be more useful than a generic demonstration because it would reflect a real vessel, cable, route and operational team.
Degraded modes must be designed in
Power cable operations have also reinforced the need to plan for degraded conditions. The monitoring arrangement should identify how it will respond to loss of a sensor, navigation uncertainty, power failure, communications loss or an obstruction during recovery.
In the North Sea Systems design, the computer monitors data quality and automatically switches to a secondary system if needed. Pressure-based depth and winch payout provide further references. A manual release can free the survey head near the surface after a power loss, while ROV-assisted recovery forms part of the contingency plan if normal recovery is not possible.
The particular engineering solution is less important than the design discipline: recovery should not depend entirely on the component that has failed. Telecom qualification should, therefore, examine those failure paths with the same care applied to normal operation.
The current system is intended for water depths down to approximately 200 meters and tidal flows of up to 4 knots. It is, therefore, not proposed as a solution for every oceanic lay. The most relevant telecom applications may be continental-shelf routes, approaches, landfalls, crossings and other areas where route congestion and the need for positional control are greatest. These are also locations where anchors, fishing activity, existing assets and seabed constraints often concentrate long-term risk.
Building the evidence for telecom use
A controlled telecom deployment offers the clearest route to building the evidence, ideally through collaboration between a cable owner, cable supplier and installation contractor. Agreeing the success criteria in advance would create a shared basis for evaluating cable interaction, positioning accuracy, data quality, operational recovery and performance in degraded conditions.
Treating such a trial as a qualification exercise rather than a product demonstration would give the industry more meaningful evidence. Comparison with established monitoring, transparent recording of limitations and appropriate sharing of the results would help cable owners, suppliers and installers judge where cable-mounted touchdown monitoring could add value.
Telecom systems have long service lives, high strategic value and little tolerance for installation damage. That encourages appropriate conservatism. In practice, conservatism means requiring evidence, defined operating limits, redundancy and recoverability. It need not exclude relevant experience from an adjacent sector.
Power cable installation has shown that the touchdown does not have to remain an inferred point somewhere behind the vessel. It can be observed, calculated, checked and recorded throughout the lay. If that capability can be qualified for telecom products, it could support earlier operational decisions, stronger installation records and a clearer view of risk at the point where the cable meets the seabed.